How long does window replacement take in Phoenix, from order to install?

About 8 weeks from first contact to finished install: across 919 install jobs from June 2025 to November 2026, the median was 60 days from booking to finish, and half of all jobs took between 42 and 75 days. Building your windows takes 2 to 3 weeks, the rest is lining up the schedule, and the install itself takes 1 to 2 days at your home.

The steps, start to finish

  1. Quote. Send photos and sizes for a virtual quote, or book a free estimate at your home.
  2. Measure. We confirm every size on site before we build, so each window fits its opening.
  3. Build. Our vinyl windows and sliding glass doors are made in house for the Arizona heat, to your exact sizes and glass choice. This takes 2 to 3 weeks.
  4. Install. Our own crew removes the old windows and installs the new ones. Installs take 1 to 2 days, and a cutback install takes 2.
  5. Warranty. Every install carries our lifetime warranty on product and installation, transferable to the second owner.

What the 60 days look like

Share of jobs Days from booking to finished install
Fastest quarter of jobs 42 days or less
Median job 60 days
Slowest quarter of jobs 75 days or more

Jobs with special shapes, large multi-slide doors, or many openings tend to take longer, because there is more to build.

Why it takes about 8 weeks

Many, many installers in this area hire subcontractors. We do not. Our own crews do every job, across 15 crews. You get the people who stand behind the work, and that is part of why it takes longer: your install waits for one of our crews, not whoever is free.

Plan around the heat

Spring is our busiest season: in the second quarter of 2026 we finished 175 install jobs, the most of any quarter (see the price index). Fall and winter are quieter.

  • Want new windows before summer? Book in January or February. At about 8 weeks, that lands your install before the first 100°F days.
  • Replacing in the fall? Expect a shorter wait, since it is our quietest season.

In 2024 Phoenix ran 113 days in a row at 100°F or hotter (National Weather Service). Windows with our LoE³-340+ glass let in about 14% of the sun's heat; see what dual-pane low-E glass does at 115°F.

Get on the schedule

Installed prices are on our pricing page: $635 to $890 per window, installed. Start with a virtual quote, a free estimate, or call (623) 231-2451.

Questions

How long does window replacement take in Phoenix? At Energy Shield, about 8 weeks from first contact to finished install. The median was 60 days from booking to finish across 919 jobs from June 2025 to November 2026, and half of jobs took between 42 and 75 days.

How long does the install itself take? 1 to 2 days at the house. A cutback install takes 2 days.

Does Energy Shield use subcontractors? No. Our own crews do every job, across 15 crews.

When should I book to have new windows before summer? Book in January or February. At about 8 weeks, that puts the install before the first 100°F days.


Written by Ennis Rushton, co-owner, Energy Shield Window & Door Company. Updated November 6, 2026.

Get a Virtual Estimate

Submit the Form Below

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
Get an Estimate for Which Products?
Accepted file types: jpg, jpeg, png, gif, webp, heic, heif, Max. file size: 25 MB, Max. files: 10.

    Factory Direct Windows

    Financing is available

    Accredited Business - BBB logoThe National Foundation Rating CouncilDWM Readers Choice Award

     

    AZ ROC 357557

    Tempe Window & Doors Contractors

    2025 Best of the Desert - AZCentral.com Community Choice Award

    2025 Best of the Desert - AZCentral.com East Valley Award

    2025 Best of the Desert - AZCentral.com West Valley Award

    TheHomeMag Certified - $5000 guarantee

    Three people sitting around a table looking at a laptop discussing replacement doors and window replacement.

    Step 1

    Design Consultation


    Our design consultants will listen to your design needs and provide a plan to improve your home.
    A man employed at a replacement windows company.

    Step 2

    Measure & Manufacture


    Project technicians ensure accuracy and answer any questions before ordering your fully customized windows.
    A man in an orange shirt standing next to a truck from a window replacement company.

    Step 3

    Installation


    Our installers treat your home as if it were their own and clean up afterwards.
    Two women discussing replacement windows at a desk in an office.

    Step 4

    Customer Care


    A robust limited warranty is backed by our commitment to make sure your windows function as expected.

    Proudly Serving Phoenix, AZ, and Nearby Areas

    We are proud to serve Greater Arizona with energy efficient replacement windows, patio doors, and entry doors. In addition to the Phoenix metro area, we also serve Northern Arizona including other areas near you.